DFS, Birstall

Live-Environment Flagship Refurbishment & Mezzanine Expansion
​
End-to-end project management of a £2.3M multi-phase retail fit-out, structural mezzanine build, and front-elevation overhaul within a live trading showroom.

Client: DFS

Location: Birstall, West Yorkshire, UK

Project Value: £2.3M

Time scale: 21 weeks (May - Oct 2026)

 

Project Overview​

Westminster Project Services provided [insert exact role, e.g., Principal Contracting / Project Management / Specialist Fit-Out Delivery] for the comprehensive 21-week refurbishment and expansion of the DFS showroom in Birstall. Working alongside 7formation Limited and specialist trade partners, our objective was to install a major new mezzanine floor, upgrade the building envelope, and modernise the retail space while keeping the showroom open and trading safely. Through strict phased segregation and out-of-hours scheduling, we delivered the entire transformation on time with zero disruption to daily customer operations.

​

The Scope

Executed across three overlapping phases from late May to mid-October 2026, the programme covered:

  • Phase 0: Site Mobilisation & Enabling Works (5 Days): Erected internal split-store hoarding, established temporary site offices, welfare cabins, and distribution boards, and completed initial service isolations and FFE clearance ahead of heavy works.

  • Phase 1: Mezzanine Installation & Rear Showroom Fit-Out (74 Days): Managed a 15-day soft strip followed by the 12-day installation of a new mezzanine floor, passenger lift, and goods lift. Coordinated high- and low-level M&E containment, HVAC ductwork, suspended ceilings, bespoke kitchen/amenity areas, and a controlled 17:00 handover of Phase 1 back to DFS.

  • Phase 2: Front Elevation, Curtain Walling & Live Retail Transformation (101 Days): Oversaw structural steelwork, entrance slab reconfiguration, and new curtain walling on the front elevation. Executed sensitive front-of-house works—including hoarding reconfigurations after 17:00, protective tunnel crash decks, floor chasing, lighting tracks, and out-of-hours flooring installation—without interrupting store trading.

  • Commissioning, Signage & Handback: Completed final M&E testing, HVAC commissioning, feature wallpapering, external signage installation, and after-hours sparkle cleans before Practical Completion and handback for client merchandising.

 

The Impact

Through disciplined phasing, proactive stakeholder coordination, and strict site controls, Westminster Project Services delivered a landmark retail transformation without compromising daily store performance. The completed showroom successfully balances complex structural engineering with a seamless, high-end customer environment.

  • Zero Trading Downtime: Strategic internal hoarding, tunnel crashdecks, and out-of-hours execution (after 17:00 and 19:00) for noisy or disruptive tasks allowed DFS to trade continuously across a 21-week live refurbishment.

  • Expanded Retail Footprint & Accessibility: Successfully integrated a new mezzanine level serviced by both a passenger lift and a goods lift, significantly increasing usable showroom capacity and back-of-house efficiency.

  • Programme Certainty: Delivered a complex, multi-contractor schedule (coordinating specialists across structural, M&E, vertical transport, and signage packages) straight into a snag-free handback for merchandising in October 2026.

​

Main entrance view of the refurbished DFS Birstall showroom looking toward the new structural mezzanine floor completed by Westminster Project Services.
Passenger lift wayfinding signage and mezzanine balcony inside the newly refurbished DFS Birstall retail store.
Ted Baker London bedroom display at DFS Birstall featuring bespoke decorative wall panelling and herringbone flooring.
Bespoke timber wall panelling, illuminated Cinesound signage, and black track lighting installed at DFS Birstall.