Behind The Scenes Tour – SeaLife Centre, Brighton

  • Client: Merlin Entertainments
  • Location: SeaLife Centre, Brighton
  • Project Value: £40,500
  • Duration: 2 Weeks
  • Project Management
  • Hands-on approach throughout
  • Tendering and Procurement
  • Overseeing flood damage repair work

Refurbish the Animal Food Preparation and Aquarists Biological Services Room at SeaLife Centre, Brighton with new and existing equipment following a flood to both areas. Works included:

• Scoping the works required, obtaining quotes and project managing the works with a hands-on approach from start to finish

• Project Budget Management

• Liaising with the Client

• Removing damaged floor screed and fitting a manhole inspection chamber

• Laying new screed allowing for a floor drain to be fitted and connected to the floor chamber

• Fitting of plinths to the floor allowing for the equipment to be raised off the floor as mitigation against any future flooding

• Fitting of white rock to the walls

• Laying of the new floor covering

• Procurement of equipment

• Stripping out redundant pipework and electrics and replacing with new to include a supply of saltwater as well as hot and cold water supply and fitting of additional sockets